Why is the summer window so tight?
Because districts and school boards want roof work done while students are away. That gives you the weeks between the last day of school and the return of staff in August. The window is short and it doesn't move. A late bid, a slow approval or a material delay can't push the work into September. So every school roofing project is really a scheduling project.
The summer break also falls inside Colorado's hail season, which runs from roughly mid-April to mid-August. Summer afternoons often bring thunderstorms, too (see how the Colorado climate wears out roofs). And the buildings aren't empty. Summer school, camps, sports programs, custodial deep cleaning, technology upgrades and other contractors all want the same weeks.
How do you work backward from the first day of break?
Start the fall before. Here's the usual sequence for a public school:
Assess in the fall
Inspect every roof section and rank it by condition. On low-slope roofs, an infrared moisture survey with core cuts shows where insulation is wet. On older buildings, test roofing materials for asbestos where Colorado rules require it. The results affect design and schedule.
Budget and approve over the winter
Fit the work into the capital plan, bond program or maintenance budget, and get board approval.
Design and specify
An architect or roof consultant usually prepares drawings and specifications: the system, insulation, drainage changes, flashings, warranty and phasing.
Bid in late winter or spring
Invitation to bid, a prebid meeting and site walk, questions and addenda, then bid opening.
Award and submittals
Contract, bonds, insurance certificates, product submittals and a schedule. Materials are ordered early so they're on hand when school lets out.
Build over the summer
Start as soon as the building is available. Work in phases, and dry in every section before the crew leaves.
Close out before staff return
Punch list, final inspections, warranties, as-built roof plans and maintenance recommendations.
Charter and private schools may not use formal public bids. But their boards face the same summer window, so the same timeline applies to you.
What does the paperwork for a public bid ask for?
It asks for bonds, insurance, licensing and campus rules, among other things. Public school construction projects come with paperwork that private work doesn't. Bid documents vary, so read each one, but expect some combination of:
- A bid bond submitted with the bid, and performance and payment bonds at award. A performance bond guarantees the contractor will complete the work.
- Insurance certificates naming the district and others as additional insureds.
- Licensing for the jurisdiction where the school sits.
- Participation goals for minority, disadvantaged, small or emerging businesses.
- Wage, safety and campus requirements. Some public projects carry wage rules. Workers on campus may need badges or background checks, and the bid may ask for a written safety plan.
- Specified products and approved equals, with substitution requests due before the bid deadline.
Truman is bonded, certified and used to public-bid paperwork. We have bonding capacity over $1M, with bid and performance bonds available. We carry $2M general liability, a $5M umbrella and workers' comp on every employee. Our Denver and regional MBE, DBE, EBE and SBE certifications can help a project meet participation goals. You can request our capability statement, insurance certificates, bonding letter, safety program and certifications, as described on our general contractors page.
Bidding direct or under a general contractor
Districts bid some school roofs directly. Many others are part of a larger renovation or addition led by a general contractor or construction manager. Then the roof becomes a subcontract. Bids, submittals and RFIs go through the GC. Roofing is coordinated with the mechanical and sheet metal trades. We work both ways. Our guide to working with a pre-qualified roofing subcontractor covers what a GC should expect from us.
What do school roofs look like?
Educational facility roofing is rarely a single system. Most schools grew in stages, so one campus can have several roof systems and ages. Original wings often have built-up and gravel roofs. Later additions and re-roofs have EPDM and TPO, sloped features and entries have metal, and some roofs have spray foam recovers. Each area has its own concerns:
| Roof area | What to watch |
|---|---|
| Classroom wings | Rooftop units and curbs, drains, joints with older or newer wings |
| Gyms and multipurpose rooms | Long spans that pond, wood floors below that can't take a leak, high interior access |
| Kitchens and cafeterias | Exhaust fans and grease, makeup air units, heavy equipment curbs |
| Science labs and shops | Exhaust stacks and fume hoods, many penetrations |
| Connectors and additions | Flashings where roofs of different heights and systems meet |
Our overview of commercial roofing systems explains each system. With a tear-off, you generally have to bring insulation up to the current energy code. That can change curb and edge heights. Re-roofs also generally need a permit, so the design should account for both.
Safety on a campus in summer
- Fenced staging and crane zones, kept away from summer program entrances, playgrounds and athletic fields
- Fire lanes and exits kept clear at all times
- Crane lifts scheduled when programs aren't arriving or leaving
- Daily cleanup, including magnetic sweeps for nails around the building
- Every crew working under our written safety program and a site-specific fall-protection plan
- Any campus rules the district sets
How is school roof repair handled during the year?
Leaks during the school year get repaired after school hours or on weekends, because not everything waits for summer. Temporary repairs keep classrooms dry until the planned project. If water is coming into a classroom, report a leak or call (720) 296-0000.
Regular maintenance keeps those calls rare. NRCA recommends inspecting low-slope roofs at least twice a year and after severe weather. Our S.M.a.R.T. maintenance program follows that schedule, with a written report for each building.
After hail, document the damage and contact your district's risk management office or insurer, since coverage arrangements vary. We document the damage, meet your adjuster on the roof and prepare a detailed scope. See after a hailstorm.
Closeout that helps the next project
A good closeout package makes the next decision easier. It includes manufacturer warranty documents, our workmanship warranty, an as-built roof plan by section, product data and maintenance recommendations. As an approved applicator, we're able to offer extended manufacturer warranties on commercial projects. Keep the package in the facilities file with the original assessment.
We work on schools and public buildings across the metro, including Aurora, Littleton and Centennial. Our projects page shows how we approach each building type. Andrew Rickert, our Operations Manager and a CPA, leads estimating; meet him and the rest of our team. Planning a summer project? Request an assessment this fall. Or send your bid invitation, and we'll confirm receipt and our bid date.
School roofing FAQs
When should a district start planning a summer roof replacement?
The fall or winter before. That leaves time for the assessment, budgeting, design and bidding. It also leaves time for award, submittals and material orders before the last day of school.
Can a school roof be replaced during the school year?
Sometimes, with work phased over weekends and breaks and strict separation from occupied areas. Summer is far easier, and most districts plan for it.
Are you bonded for public school work?
Yes. Truman has bonding capacity over $1M, with bid and performance bonds available. We're used to public-bid paperwork and prequalification forms.
Do you bid directly to districts or through general contractors?
Both. We bid roof replacements directly. When the roof is part of a larger project, we work as a pre-qualified roofing subcontractor.
What if hail damages the roof just before school starts?
Stop active leaks with temporary repairs, and document the damage with dated photos. Then notify your risk management office or insurer. Permanent repairs follow once the scope is agreed.
What happens if an old school roof contains asbestos?
Older roofing materials are tested before tear-off where Colorado rules require it. If asbestos is found, its removal is planned and handled under those rules, before or alongside the roofing work. That's why testing belongs in the fall assessment.